  • Works will continue in the Urban Orchard area with the installation of the concrete tables, completion of the gabion baskets, installation of the last of the seating, and a general tidy up.
  • Landscaping works in the Central Square area will continue with planting, installation of seating and painting of the wayfinding.
  • The planter troughs in front of the Library will be installed and planted out.
  • Works will continue in the Museum area with the installation of irrigation, and the mulching and planting of the Beaufort Street planter box. Turf will be laid on the earth mounds in this area, and in the area in front of the Art Gallery administration building.
  • The vent demolition near the Roe Street overpass will continue with the removal of the block work underneath the slab and the fabrication of the vents.
  • Mulching and planting in the area in front of PICA.
  • General tidy up and demobilisation from site will commence.
  • Various electrical works continue to be undertaken throughout the site.


William Street
Works

  • Connection of electrical services at Lot 20 and 1306.
  • Floor sanding at Lot 1297.
  • Paving and fencing at Lot 1115.
  • Final roof trims and painting at Lots 1297 and 1115.
  • Removal of hoardings at Lots 1297 and 1115.
  • Brickwork to walls at Lots 1279-1283 and Lot 404.
  • Ablutions to Lot 404.
  • Continue electrical and plumbing works at Lots 1279-1283 and Lot 404.
  • Continue facade works at Lots 1279-1283 and Lot 404.
  • Continue carpentry and ceiling work at Lots 1279-1283 and Lot 404.