Works

  • Works will continue in the Urban Orchard area with the installation of porous paving, installation of the last section of turf, filling of planter boxes and planting of trees.
  • Landscaping works in the Central Square area will continue with mulching, planting, and installation of seating.
  • Works will continue in the Museum area with the installation of irrigation and turf to the earth mounds, and work on the Beaufort Street planter box.
  • Work will continue in the new Wetland area with the painting of the stairs and installation of tactile paving.
  • The vent demolition near the Roe Street overpass will continue with the removal of the block work underneath the slab and the fabrication of the vents.
  • Mulching and planting in the area in front of PICA.
  • Various electrical works continue to be undertaken throughout the site.

William Street

Works

  • Painting at Lot 1297.
  • Internal works and ablutions at Lot 1297.
  • Painting and carpentry works at Lot 1115.
  • Storm water and sewer services at Lots 1279-1283 and Lot 404.
  • Electrical and plumbing works at Lots 1279-1283 and Lot 404.
  • Facade works at Lot 1279-1280.
  • Carpentry works at Lots 1279-1283 and Lot 404.